Orinda rehab project uses eco-friendly geopolymer to restore aging culverts

The city of Orinda sits just nine miles east of Oakland, Calif., within the Diablo Mountain Range. Local roads wind through the rolling hills next to many main streams that run through the mountain range. These tributaries empty into the Pablo Reservoir and the Upper San Leandro Reservoir.

Before and after culvert rehabilitation.

These seasonal streams are environmentally sensitive for local aquatic life and drinking water derived from the reservoirs. Many large culverts were installed in the 1940s and ‘50s to take these streams under the roads; they are now showing signs of fatigue and some with their inverts completely corroded.  

The city recognized the corrosion as an issue and called on Walnut Creek-based HDR Inc. to evaluate which trenchless technology would be a feasible repair option. HDR selected spray-applied geopolymer mortar based on its ability to minimize environmental impact, as well as delivering the ability to reinstate flow through the culvert immediately after installation. It also maintained the hydraulic capacity of the rehabilitated culverts and had a lower overall cost of installation.  

The city required a permit from the California Regional Water Board for the project and the work could occur only during the non-rainy season. The permit required ecotoxicity data on the selected material, to determine the time required before the stream could start flowing through the culvert after rehabilitation. 

National Plant Service, a Carylon Company, was the contractor selected to complete the rehabilitation, with GeoTree Solutions’ GeoSpray 61 as the chosen product. The decision was made based on the material holding properties that enabled flow to be reinstated after only two to four hours of curing. GeoSpray 61 is also NSF 61 certified for drinking water standards and has a high flexure strength, which meant the installed thickness of the material could be reduced, compared to other materials and systems on the market. 

In preparation for the rehabilitation work, a diversion was put in place that would run the summer creek flow through a gravity flow bypass pipe without the use of a pumping system, which could negatively affect aquatic life. The bypass did not change the flow of the creek up and down stream during the rehabilitation, did not increase turbidity or increase erosion from the discharge of the bypass pipe. The bypass was installed directly through the pipe being rehabilitated which allowed for the gravity flow to occur. 

“A temporary dam was installed using gravel filled geotextile bags and plastic,” said Daniel Solano, National Plant service manager. “This directed the water from the upstream side of the culvert into the bypass pipe. The bypass pipe exited the culvert and drained into the creek downstream.”  

The project consisted of three culverts at different locations within the city of Orinda, each sitting on different tributaries. One was a 72-inch by 110-inch arch culvert, the other two were corrugated metal pipe culverts measuring 66 inches and 60 inches. All mixing and pumping operations were carried out on a spill control pad within a tarp tent to minimize dust release. A disposal container sat next to the mixing area for the cleaning of hoses that conveyed the material into the culvert to the spray head applying the material. 

GeoTree Solutions engineers calculated the thickness required to adequately line the culverts: 1.5 inches for the 60-inch and 66-inch diameter pipe, and 1.75 inches for the 72-inch x 110-inch arch culvert.  

The invert was partially deteriorated in two of the culverts. These required filling with GeoSpray 61 to eliminate water movement under the pipe, which could cause issues later. Again, GeoSpray 61 was used to eliminate any ecotoxicity issues with stream. All the geopolymer was hand-sprayed with the finial ½ inch thickness of the structural rehabilitation spin casted. 

The construction equipment, which measured 10 feet by 75feet, was stagged along the street to ensure it did not affect traffic flow. For the arch culvert, the equipment was along the side of a residence driveway, but access was still possible. Work could be carried out between 8:00 a.m. and 4:00 p.m. to eliminate disruption to the residences. 

Each culvert, from mobilization to completion, took just five days. 

GeoTree Solutions, part of CRITICA Infrastructure, is a leading global provider of highly engineered solutions for repairing, rehabilitating, strengthening and protecting critical infrastructure spanning the water and wastewater, oil and gas, industrial, and civil sectors. The company’s premium geopolymer solutions and onshore/offshore RenewWrap structural strengthening products can be applied to culverts, sewers, and manholes, and civil structure repairs such as pilings, bridges, wharfs, silos, tanks, buildings, monuments, and towers.