Berkeley County, S.C., Red Bank Road sewer project on track for April 2025 completion
(UI) — Berkeley County’s Red Bank Road Gravity Sewer Project in Goose Creek is progressing toward its goal of increasing sewer capacity and preventing overflows.
The project, which began in spring 2022, has faced significant delays but now has a tentative substantial completion date of April 2025.
The main objective is to install a large gravity sewer line along Red Bank Road, between Sunrise Boulevard and Henry E. Brown Jr. Boulevard. Recent progress includes the removal of the old curb line and milling and grading of the road in preparation for resurfacing.
To address delays, the County has brought in new contractors—Palmetto Site Works and Sanders Brothers Construction. All curbing and milling work is expected to be completed by late February, with resurfacing set to begin soon after. The resurfacing work will mark the final phase of the project.
The total project cost is approximately $13 million.
Related News
From Archive

- Authorities investigating trench collapse that killed worker in Ashburn, Va.
- OSHA fines Calif. company for violations that led to fatal trench collapse
- Greenpeace must pay $667 million to Energy Transfer over pipeline protests, jury finds
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
- NTSB publishes preliminary report on fatal gas pipeline explosion in Lexington, Mo.
- Maryland lawmakers push to curb BGE pipeline spending, citing safety and cost concerns
- Charlottesville, Va., to begin work on 24-inch water line for Rivanna River crossing
- Mass. governor slams Trump for ‘dangerous delay’ of $50 million in lead pipe replacement funds
- City of Albuquerque halts fiber optic construction in response to damage, complaints
Comments