According to Metrolinx, crews in Toronto have begun the final phase of construction for tunnels that will connect the Eglinton Crosstown West Extension to the existing terminus of the Eglinton Crosstown LRT (Line 5 Eglinton) at Mount Dennis Station in Toronto, Canada.
Last year, the contract to design and build the second underground segment of the Eglinton Crosstown West Extension was awarded to Strabag Inc.
The 1,640-foot (500-meter) twin tunnels are being built using the sequential excavation method, which is often used for smaller sections of tunnels, Metrolinx reported. With this method, the area to be tunneled is divided into smaller sections and excavated in sequence. Concrete is then sprayed onto the tunnel walls as the sections are excavated to reinforce the exposed walls. About one to two meters of tunnel are excavated each day.
Last year, twin tunnel boring machines Renny and Rexy completed a two-year project in which they excavated a 3.91-mile (6.3-kilometer) stretch of the western tunneled section of the line. At the end of the twin tunnel section is where the future rapid transit line will transition to an above-ground section.
The extension will make Line 5 Eglinton another expansive east-west rapid transit line for the Greater Toronto Area (GTA), running all the way from Scarborough, through midtown Toronto and into Mississauga. The project will add seven new stations to Line 5 Eglinton’s 25 stations and stops.
Related News
From Archive
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- Oil pipeline struck during fiber optic construction spills into L.A. storm drains
- Fiber drilling strike triggers major sewer failure, lawsuits in Florida
- OSHA cites Alabama builder after fatal trench collapse
- Utility strike at center of Dallas explosion investigation
- Race Communications breaks ground on Bakersfield fiber network
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- Inside Infrastructure: Utility locators warn of systemic failures in damage prevention process
- Senate passes PIPELINE Safety Act aimed at strengthening buried utility protection

Comments