Trans Mountain completes pipe pullback for Mountain 3 HDD in Fraser Valley
(UI) — Trans Mountain successfully completed the pipe pullback for the Mountain 3 Horizontal Directional Drill (HDD) in the Fraser Valley between Hope and Chilliwack, BC.
To complete the expansion project, there are several remaining steps including obtaining outstanding approvals from the Canada Energy Regulator (CER). With the appropriate approvals and completion of remaining construction activity, Trans Mountain will commence transporting crude oil on the expanded system.
The commencement date for commercial operation of the expanded system will be May 1, 2024. Trans Mountain anticipates providing service for all contracted volumes in the month of May.
After commencement of operation of the Expansion Project, Trans Mountain will continue cleanup, reclamation, road and civil work.
Related News
From Archive
- Tunnel boring machine ‘Clack-A-Mole’ nears one-third completion in Oregon outfall project
- Lynchburg, Va., breaks ground on largest-ever Blackwater CSO tunnel project
- Wyo-Ben’s Max Gel, Max Bore HDD system boost drilling efficiency, performance
- Texas A&M weighs underground transit plan with Elon Musk's Boring Co. to reduce campus traffic
- Colorado's Wolf Creek Pass tunnel drainage project begins
- Wisconsin proposes new PFAS drinking water standards to align with federal rules
- Elgin, Ill., joins EPA drinking water initiative to accelerate lead pipe replacement
- Dog River pipeline replacement in Oregon improves water supply with new HDPE pipe
- New Portable Welding System From Miller
- Excavator Causes Puerto Rico Power Outage
Comments