(UI) — The City of Orange Beach has announced the completion of a $6.09 million RESTORE project for the Orange Beach North Sewer Force Main Upgrade with oversight conducted by the Alabama Department of Conservation and Natural Resources (ADCNR).
The project constructed approximately 8 miles of sewer force main from a point on Highway 180 in Orange Beach, Alabama, to an existing lift station on County Road 12.
The Orange Beach City Council awarded the contract to R&B Contracting Company Inc. The work began in April 2022 and was completed in August 2023. The Orange Beach area that benefits by this sewer main upgrade includes areas north and east of Wolf Bay to Josephine as well as areas directly served by the force main. Implementation of this project will prevent failures in the existing main and decrease the use of on-site septic systems.
Orange Beach Mayor Tony Kennon said the sewer upgrade is a welcome addition around Wolf Bay.
“Sewer lines may be out of sight, out of mind but it’s a critical system that needs to be maintained properly,” Mayor Kennon said. “Having 8 miles of the sewer force main upgraded from pipes that were installed in the late 80s will ensure the protection of Wolf Bay to our north and better serve residents in that area for decades to come. Wolf Bay has been recognized by the ADEM (Alabama Department of Environmental Management) and the EPA as an ‘Outstanding Alabama Water.’ This project will help protect that designation. I commend city staff for making this project a reality along with support from our state and federal agencies.”
The grant was funded under the Resources and Ecosystems Sustainability, Tourist Opportunities, and Revived Economies of the Gulf Coast States Act of 2012 (RESTORE Act), a federal law created by Congress on July 6, 2012 enacted in response to the Deepwater Horizon oil spill. The RESTORE Council consists of the governors of five Gulf Coast states (Alabama, Florida, Louisiana, Mississippi, and Texas) and the cabinet heads of six federal agencies (the U.S. Department of Agriculture, U.S. Department of the Army, U.S. Department of Commerce, U.S. Department of Homeland Security, and U.S. Department of the Interior, as well as the U.S. Environmental Protection Agency) Conservation Commissioner Chris Blankenship represents Governor Ivey on this council.
Related News
From Archive
- Tunnel boring machine ‘Clack-A-Mole’ nears one-third completion in Oregon outfall project
- Lynchburg, Va., breaks ground on largest-ever Blackwater CSO tunnel project
- Texas A&M weighs underground transit plan with Elon Musk's Boring Co. to reduce campus traffic
- Wyo-Ben’s Max Gel, Max Bore HDD system boost drilling efficiency, performance
- Federal court halts permits for 32-mile Tennessee gas pipeline project
- Wisconsin proposes new PFAS drinking water standards to align with federal rules
- Elgin, Ill., joins EPA drinking water initiative to accelerate lead pipe replacement
- Dog River pipeline replacement in Oregon improves water supply with new HDPE pipe
- Leaking wastewater systems named top source of San Diego River contamination, study finds
- New Portable Welding System From Miller
Comments