May 2019 Vol. 74 No. 5

Features

Rock, Weather, Tight Deadlines are No Match for Horizon Pipeline

Pipeline construction projects across America have flurried in recent years, with miles of natural gas line being added almost daily. The bulk of new lines is being constructed in the prolific Permian Basin, with midstream energy companies, like Targa Resources Corporation, expanding to support growing demand for natural gas and liquified natural gas (LNG) exports.

One contractor involved with the construction of Targa’s massive Grand Prix Natural Gas Liquids (NGL) Pipeline is Horizon Pipeline & Construction, based in McAlester, Okla. Established in 2015, the young company already employs a team of about 550 people. According to Horizon Pipeline Operational Manager David Baggs, timing couldn’t have been better. “I’ve been in pipeline for 22 years, and the past few are among the best I can remember,” he said.

Horizon Pipeline crews can be found working throughout Texas, Colorado and Mexico, but a few of the company’s recent projects have been close to home. The team has been instrumental in helping to expand the Grand Prix Pipeline into southern Oklahoma to integrate Targa’s SouthOk and North Texas G&P assets, and connect to a new Hickory Hills processing plant. Over seven months, crews have laid more than 110 miles of NGL pipe, including an extremely challenging 30.3-mile stretch of 10-inch steel NGL line near McAlester.

Hickory Hills challenge

Sandstone—and lots of it—was in store for the Horizon Pipeline crew on the Hickory Hills stretch of the Grand Prix Pipeline. Baggs estimated around 70 percent of the installation was in rock and rough terrain.

“McAlester is home for us, so we knew how tough the ground conditions were going to be,” he explained. “We decided pretty quickly that using a rock trencher was going to be the most efficient way to handle the bulk of the open trench work.”

Horizon Pipeline typically subcontracts any trenching or horizontal directional drilling (HDD) work on its projects. However, the team decided to rent equipment and perform all the open-cut work themselves.

“There are 20 miles of open-cut work and 10 miles of trenchless installs on this job,” Baggs said. “Subbing both would have had a significant impact on our productivity and efficiency. So we decided to look at renting a large trencher.”

After a bit of research, Horizon Pipeline settled on a Vermeer T855 Commander 3 track trencher rented from Vermeer Great Plains in Catoosa, Okla. “Given the amount of rock we were working in, a few of our guys were a bit concerned that the T855III was too small for the job, but it ended up having plenty of power and did a nice job cutting through the hard rock,” he commented.

Crew members used the trencher with an 8-foot boom to cut a 36-inch wide trench, 5-feet deep before laying the 10-inch steel NGL pipeline. In common ground conditions for the area, they were able to open 1,500 to 2,500 feet a day. When working in harder rock, production slowed to between 800 to 1,200 feet a day.

“Given the ground conditions, we were thrilled with the production,” expressed Baggs. “We went through some teeth throughout our rental, but that’s to be expected.”

More importantly, Baggs said renting the rock trencher was the right decision. “There was no way we would have been able to cut a trench using track hoes alone cost-effectively, and for the time we ended up being on the job, using a subcontractor would have been even more cost-prohibitive. Ideally, we’ll end up purchasing a few track trenchers as we continue to grow.”

Unexpected delays

While the work went according to plan, the project did take Horizon Pipeline’s team longer than expected because of bad weather—and needing to complete another stretch of pipeline for Targa. “The fall of 2018 was one of the wettest we’ve had around here,” Baggs said. “It rained several days almost every week we spent on this job. There was a week we got nearly 40 inches of rain. It was terrible!

“We had a semitruck that was completely demolished in the floods, and one of our HDD subcontractors lost a reclaimer,” he continued. “They were set up on the top of a 15-foot river bank. The river rose so quickly, they couldn’t get the machine moved out of the way in time. I’ve never seen anything like it.”

Heavy rains forced the trencher crew members to shut down for several days. However, they operated so efficiently on the days they were able to run, they managed to make up most of the time lost. “There is no way of knowing what the weather is going to do, so I’m sure glad we decided to rent a rock trencher,” Baggs added. “Without it, we would have been even further behind.”

Horizon Pipeline was awarded another project for the Grand Prix Pipeline Oklahoma extension, a 50-mile stretch between Velma and Davis, Okla. “That job had a very tight deadline, so we had to pull a lot of people from the Hickory Hills job over,” said Baggs. “For the most part, we kept the trencher going, but we needed just about everyone else on the other project to keep everything on schedule.”

Crews wrapped up the Hickory Hills job and the 50-mile stretch in about nine months despite setbacks. The team also used the trencher on the 50-mile project, where it was used to dig another 30,000 feet.

Baggs points out that “we have a lot more pipeline work coming up in West Texas, and we may need to rent another trencher as we fight with the hard caliche rock in that part of the state.”

FOR MORE INFORMATION:

Horizon Pipeline & Construction, (918) 429-1200, horizonpandc.com

Vermeer Corp., (888) 837-6337, vermeer.com

Related Articles

From Archive

Comments

{{ error }}
{{ comment.comment.Name }} • {{ comment.timeAgo }}
{{ comment.comment.Text }}