The historic Pacific Coast Highway runs along some of the most beautiful coastlines in the United States. Through Newport Beach, California, it’s known simply as the PCH. It winds north along the coast through upscale neighborhoods and shopping areas toward Los Angeles. Visitors travel from around the world to cruise the highway and admire the communities nestled into the coastline of the ocean.

Below the stunning scenery ran a decades-old sewer main in urgent need of repair or replacement. For a city that relies heavily on income from tourism, a sewage leak next to the ocean would be catastrophic. The Newport Force Main Rehabilitation project aimed to replace that system before the worst could happen. ISCO Industries provided high-density polyethylene pipe, McElroy fusion equipment, and expertise for the job.

ISCO HDPE choice to run under historic highway in California

ISCO representative Joe Chammas added, “It was a high profile job with extensive risk. ISCO’s size and national high density polyethylene (HDPE) pipe supply presence was required by the contractor in order to have a truly qualified supplier to support a project of this size and exposure.”

HDPE was a clear choice to replace the aging system. “It offers excellent flow characteristics, exceptional corrosion resistance, and reliability,” Chammas explained. “The pipeline will be leak-free, which is crucial because it’s installed under a major historic highway.” ISCO mainly supplied 8,300 feet of 32-inch IPS DR26 and 3,900 feet of 36-inch IPS DR26 along with fittings ranging from 11 ¼ degree elbows through 45 degree elbows, including 22 ½ degree elbows and concentric reducers. ISCO also provided nearly 50 fabricated spooled access tees, ranging in size from 36-inch DIPS down to 32-inch IPS. Not only that, ISCO fabricated stainless steel tops as part of the access tees. “We were able to provide alternative options for fabricating the complicated manway structures that were a major part of the force main pipeline,” said Chammas. “The pipeline size, length, and layout of a double barrel pipeline installed in a single trench required the availability and support of multiple HDPE fusion machines in order to install the pipeline in a timely manner. ISCO’s large fusion equipment fleet met the contractor’s needs. We never said no and always made it happen.”