Columbia Gas plans spring line replacement through Upper Arlington, Ohio
(UI) — Columbia Gas will begin replacing aging high-pressure pipelines in Upper Arlington next spring as part of a regional safety upgrade, the utility told city officials.
The first phase, scheduled to start in Spring 2025, calls for installing 12-, 16- and 20-inch steel mains equipped with modern safety valves. The new lines will serve a broad area beyond city limits.
Crews will enter Upper Arlington at Zollinger Road near Ohio State’s west campus, then proceed south on North Star Road, west on Ridgeview Road, south on Brandon Road, and west on Northam Road to Northwest Boulevard.
Plans also include two above-ground utility stations: a replacement facility on Brandon Road and a new station on Ridgeview Road.
Columbia Gas said it will mail construction notices, hold public meetings, and maintain office hours to keep residents informed before and during the work.
Related News
From Archive

- 290-mile gas pipeline expansion proposed across Georgia, Alabama and South Carolina
- $227 million Garnet Valley water project advances, set to create 73,000 jobs in Nevada
- Pasadena, Calif., undergrounding project could take 500 years to finish
- Construction underway for $1.4 billion, 60-mile water pipeline in Chicago
- HDD industry faces challenges as cities push back on fiber drilling disruptions
- Gehl and Mustang offer world’s largest skid loader
- Growing Pains and Gains
- Authorities investigating trench collapse that killed worker in Ashburn, Va.
- Pasadena, Calif., undergrounding project could take 500 years to finish
- $227 million Garnet Valley water project advances, set to create 73,000 jobs in Nevada
Comments