Portland's $2 billion Bull Run Filtration Project halts construction after permit denial
According to The Oregonian/Oregon Live, Portland city officials have paused construction on its $2 billion Bull Run project after failing to secure a crucial land-use permit required for construction to move forward. The project, first approved in 2017, includes plans for a new filtration plant and associated water pipelines to comply with EPA regulations that require removal of certain contaminants found in drinking water samples.
On Jan. 22, the Land Use Board of Appeals sided with opponents, denying the conditional land-use permit, with the application now being sent back to Multnomah County for further review. City officials say the county review process could take up to 120 days, during which construction will stop.
The Bull Run water filtration plant lacks proper zoning due to its location in a section of forest owned by the city, which is why it requires a conditional land-use permit.
It was one of several locations the city considered when planning started nearly 10 years ago.
The project has faced opposition from some who claim that construction on the filtration plant and water pipelines will harm the area’s natural resources. Due to opposition and other factors, the filtration plant has seen several delays, causing the cost estimate to surge to $2 billion from the originally approved $500 million.
Portland officials finally broke ground on the project last year, leaving just over two years to complete construction before its September 2027 deadline.
Related News
From Archive
- 27 pipeline safety violations tied to deadly Pa. chocolate factory explosion
- Fatal trench collapse in Mass. leads to $4.6 million OSHA penalty, dozens of violations
- OSHA investigates fatal trench collapse at Conroe construction site
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- 11-mile Texas pipeline replacement upgrades 72-in. PCCP to 102-in. steel
- Alaska fiber buildout to expand broadband in rural communities
- 11-mile Texas pipeline replacement upgrades 72-in. PCCP to 102-in. steel
- Fatal trench collapse in Mass. leads to $4.6 million OSHA penalty, dozens of violations
- Texas811 launches real-time excavation detection to prevent utility strikes
- Race Communications breaks ground on Bakersfield fiber network

Comments