Calgary on the brink of water crisis after major pipeline break
(UI) — The largest city in Alberta is confronting a potential water shortage following a significant pipeline rupture. Calgary officials are urging residents to drastically reduce their water usage immediately, according to Reuters.
On June 5, a crucial pipeline serving 1.2 million residents burst, inundating streets, sports fields, and a portion of the TransCanada Highway, which is still closed. The city’s water reservoirs and distribution system have been critically impacted, city officials said.
"Calgary is currently using more water than it can produce. If Calgarians do not reduce our water use, we are at risk of running out," officials told Reuters.
The heart of Calgary, which houses many of Canada's oil and gas companies, is particularly affected. Crews have been unable to access the damaged section of the pipeline, known as a feeder main, to commence repairs or identify the cause of the rupture. However, they are hopeful that access will be gained later on Friday, according to the statement.
Residents in the Bowness area are under a boil water advisory, and businesses have been instructed to halt non-essential water use. Outdoor watering has been prohibited, and residents are being asked to delay using dishwashers and washing machines and to shorten their showers.
The affected 11-kilometer (6.8-mile) feeder main, installed in 1975, is one of Calgary's most critical and substantial water supply lines. "The broken feeder main is large enough to drive a truck through," Calgary Mayor Jyoti Gondek remarked at a Thursday press conference. "It's a significant piece of infrastructure."
Mayor Gondek assured that crews are working continuously, and repairs are expected to commence within a day or two once the break is accessed.
Related News
From Archive
- Tunnel boring machine ‘Clack-A-Mole’ nears one-third completion in Oregon outfall project
- Explosion in underground PG&E vault leaves one dead in Richmond, Calif.
- Sinkhole in Texas town accrues over $800,000 in sewer rehabilitation costs
- Tennessee pipeline gets initial FERC approval despite environmental concerns
- Water and Sewer Damage Awareness Week highlights infrastructure challenges
- Wisconsin proposes new PFAS drinking water standards to align with federal rules
- Elgin, Ill., joins EPA drinking water initiative to accelerate lead pipe replacement
- GasTracker Accurately Locates Plastic Gas Pipes
- Florence, S.C., to fund $537 million sewer, water upgrade with bonds and 5% rate hike
- Union County, Ga., breaks ground on $20.5 million fiber broadband expansion project
Comments