Stronghold Engineering wins $208 million Grand Canyon waterline rehabilitation contract
(UI) –The National Park Service (NPS) is preparing for a multi-year $208 million rehabilitation of the Transcanyon Waterline (TCWL) and related upgrades to the associated water delivery system within the inner canyon and South Rim of Grand Canyon National Park. This critical investment will ensure the park is able to meet water supply needs for the next 50 plus years, supporting 6 million annual visitors and approximately 2,500 year-round residents. The NPS awarded the $208 million construction contract on to Stronghold Engineering, Inc. of Perris, Calif.
Initial activity in late spring and summer 2023 will focus on establishing construction infrastructure and staging areas in the Grand Canyon Village Area on the park’s South Rim. The NPS does not anticipate restrictions or closures in 2023 that would impact visitors. The TCWL replacement is projected for completion in 2027.
“This huge undertaking is an example of the work taking place in national parks across the country to repair or replace vital infrastructure that provides visitors with safer and more enjoyable experiences,” National Park Service Director Chuck Sams said. “For too long, large scale needs in national parks could not be properly addressed due to a lack of funding. Bipartisan commitment from funding sources, including the Great American Outdoors Act and the Federal Lands Recreation Enhancement Act, is truly making a difference, and enabling the National Park Service to effectively tackle critical upgrades.”
The NPS is replacing the TCWL because it is beyond its expected useful life, experiences frequent failures, and requires expensive and continuous inner canyon maintenance work to repair leaks. Since 2010, there have been over 85 major breaks in the TCWL that have disrupted water delivery. Costs for a single isolated break often exceed $25,000.
Conditions in the inner canyon include extreme terrain and high temperatures which increase risk to employees during repair operations. The system also supplies water for fire suppression for all South Rim and inner canyon facilities, including over 800 buildings listed in the National Register of Historic Places.
Originally built in the 1960s, the TCWL is a 12 ½-mile waterline that provides the potable water for all facilities on the South Rim and inner canyon facilities within the park. The TCWL project will relocate the water intake for the water delivery system from Roaring Springs to Bright Angel Creek near Phantom Ranch. This location will greatly reduce the length of the TCWL and eliminate a portion of the current waterline north of Phantom Ranch that experiences the most frequent failures. The water intake at Roaring Springs will continue to provide water to the North Rim.
The project includes:
- Construction of an auxiliary hangar, helicopter landing pad, and contractor support area at the park helicopter base in order to support inner canyon construction.
- Construction of a 1 million-gallon per day water treatment plant at the South Rim and a smaller water treatment plant at Phantom Ranch.
- Replacement of the water distribution system at Havasupai Gardens.
- Replacement of approximately 3 miles of waterline and the upgrade of approximately 3 miles of electrical supply line from Havasupai Gardens to Phantom Ranch.
- Construction of a water intake system and pumping station and local water treatment plant for the Phantom Ranch area.
- Replacement of the water and electrical distribution systems at Phantom Ranch.
Related News
From Archive
- OSHA cites Florida contractors for trench safety violations at sewer and excavation sites
- Cadiz to reuse steel from terminated Keystone XL pipeline for California groundwater project
- Lynchburg, Va., breaks ground on largest-ever Blackwater CSO tunnel project
- Biden-Harris administration invests $849 million in aging water infrastructure, drought resilience
- The EPA announces $6.2 billion in funding for Iowa and Kansas water infrastructure
Comments