Court upholds block on 72-mile pipeline, halting 40 million gallons of water to Colorado residents
(UC) — The Colorado Court of Appeals has upheld Larimer County’s decision to deny the permit tied to the construction of a 72-mile pipeline meant to funnel water from the Cache La Poudre River to residents in Denver, Colorado, the Denver Post reported last week.
The appeals court's decision means that Larimer County's February 11, 2019, denial of Thornton's plan to lay a 48-inch-diameter pipe across 27 miles of county remains in effect. The remaining $423 million pipeline would pass through Weld and Adams counties, according to the Denver Post.
The city said the pipeline — which would transport 40 million gallons of water per day — is necessary to avoid the degradation of water quality which would happen by flowing the water through Fort Collins in the Poudre River.
However, residents argued that the water should flow through Fort Collins before being captured near Windsor and piped south by Thornton.
Thornton purchased the Cache la Poudre River water rights northwest of Fort Collins in 1985, CBS Colorado reported. And, with the city’s rapid growth in the last decade or so of nearly 150,000 people, it said accessing the water is vital to serving future residents.
Initially, Thornton filed a district court lawsuit against Larimer County two months after the denial. The commissioners' decision was upheld by a judge in Larimer County District Court. The city then appealed the decision to the Colorado Court of Appeals.
Thornton said it is critical to eventually obtain the water it owns, informing developers a few years prior that if it cannot obtain enough water, it may have to stop issuing building permits.
Related News
From Archive
- North America 2024 Pipeline Construction Outlook: New LNG Terminals Lead Call for More Pipelines
- DeLa Express seeks FERC approval for Permian-to-Louisiana gas pipeline project
- OSHA penalizes Houston contractor over safety violations resulting in worker's death
- Fiber infrastructure has no known expiration date, Fiber Broadband Association research concludes
- Nevada OSHA fines Elon Musk's Boring Company over safety violations in Vegas tunnel project
- Michigan lawmakers introduce bills to create septic codes throughout the state
- Indiana American Water to gain 8,000 water customers with Silver Creek Water acquisition
- New York State OKs $57.8 million underground transmission line linking Nanuet to West Nyack
- Arkansas governor allocates $42 million for water infrastructure projects
- Federal judge finds Flint, Mich, in contempt over lead water pipe crisis
Comments