Stantec secures contract to upgrade water treatment plant in Canada
Stantec has been awarded the engineering during construction, and commissioning portions of the Buffalo Pound Water Treatment Plant Renewal Project (BPWTP) in Saskatchewan, as part of the Graham-Aecon Joint Venture.
Together with its partners Graham, Aecon, and Associated Engineering (AE), Stantec led the engineering design of the $273 million comprehensive upgrade to the BPWTP, using the progressive design-build delivery model. This is the first time this delivery model has been employed in Canada for water infrastructure.
The project is owned by the Buffalo Pound Water Treatment Plant Corporation (BPWTP Corporation) and is now proceeding with construction. It will deliver an upgraded water treatment plant for the 260,000 customers in the cities of Moose Jaw and Regina, plus users of SaskWater and Buffalo Pound Provincial Park. The BPWTP is located approximately 30 km (19 miles) northeast of the City of Moose Jaw.
Commissioned in 1955, the plant has undergone three major capacity and process improvements since its original construction, with the last capacity increase completed in 1989. The plant’s infrastructure elements are nearing the end of their operational life-cycle and this renewal project will help tackle climate-related raw water conditions, evolving regulatory requirements, help prevent loss of water supply, and address dated water treatment technologies, all to simplify operations and increase capacity to meet future demands.
Stantec will be involved in construction inspections as well as start-up and commissioning activities. A key component of the project’s overall engineering design was to reuse much of the existing infrastructure, reducing construction cost and minimizing the construction of a new building footprint.
“We’re incredibly proud of our design team and partners for their work on this project,” Gillian Edwards, Stantec’s design manager for the BPWTP renewal, said. “This is a live operating plant that can’t experience long shutdown periods. Our design team has been working closely with our construction partners and the BPWTP Corporation to sequence construction and commissioning activities. This way we can ensure physical upgrades are completed with minimal impact to current water production.”
Stantec has completed an Issued for Construction (IFC) package for the Plant Renewal that includes updated treatment processes to address regulatory requirements into the future. Stantec’s work on the first phase included design and regulatory approval support. Stantec’s architects also collaborated with water treatment plant engineers to design a new administrative building for BPWTP Corporation staff. This building will connect the plant’s operations, maintenance, and management groups, improving team cohesiveness.
The Stantec-Graham-Aecon-AE partnership has delivered more than 30 alternative delivery projects together, valued at over $2 billion combined. Approximately two-thirds of the Western Canadian population drinks water from treatment plants delivered by this group of consultants, who have completed projects in Saskatoon, Edmonton, Calgary, Winnipeg, and Vancouver.
The project is expected to be complete in 2025.
Related News
From Archive
- Tunnel boring machine ‘Clack-A-Mole’ nears one-third completion in Oregon outfall project
- Texas A&M weighs underground transit plan with Elon Musk's Boring Co. to reduce campus traffic
- Lynchburg, Va., breaks ground on largest-ever Blackwater CSO tunnel project
- Wyo-Ben’s Max Gel, Max Bore HDD system boost drilling efficiency, performance
- Federal court halts permits for 32-mile Tennessee gas pipeline project
- Wisconsin proposes new PFAS drinking water standards to align with federal rules
- Elgin, Ill., joins EPA drinking water initiative to accelerate lead pipe replacement
- Dog River pipeline replacement in Oregon improves water supply with new HDPE pipe
- Leaking wastewater systems named top source of San Diego River contamination, study finds
- New Portable Welding System From Miller
Comments