Idaho nuclear waste treatment plant faces more setbacks
(AP) — A nuclear waste treatment plant in eastern Idaho had two unanticipated shutdowns this year, U.S. officials said Tuesday, continuing a lengthy history of setbacks.
Trent Neville of the U.S. Department of Energy said they're working on the problems at the Integrated Waste Treatment Unit at the department’s 890-sq mile (2,300-sq km) site that includes the Idaho National Laboratory. The plant might start operating later this year.
Neville told members of the Environmental Management Site-Specific Advisory Board and Idaho Cleanup Project that the plant ran out of liquid nitrogen in January, and also had a rapid automatic shutdown while testing with a simulant material in February.
The plant was built to treat 900,000 gallons of sodium-bearing, radioactive waste from processing spent nuclear fuel to recover highly enriched uranium. The waste is in tanks above the Eastern Snake Plain Aquifer that supplies water to cities and farms.
The department is paying fines to Idaho for missing a deadline to convert the liquid waste into solid material as stipulated in a 1995 agreement that was the culmination of a series of federal lawsuits.
Idaho, because of the missed deadline, is preventing the department from bringing in research quantities of spent nuclear fuel to be studied at the lab.
Related News
From Archive
- North America 2024 Pipeline Construction Outlook: New LNG Terminals Lead Call for More Pipelines
- Challenges of repairing rural water lines in urbanizing areas
- OSHA penalizes Houston contractor over safety violations resulting in worker's death
- Fiber infrastructure has no known expiration date, Fiber Broadband Association research concludes
- Nevada OSHA fines Elon Musk's Boring Company over safety violations in Vegas tunnel project
- Indiana American Water to gain 8,000 water customers with Silver Creek Water acquisition
- Nevada high court empowers water authority to shape underground resource management
- New York State OKs $57.8 million underground transmission line linking Nanuet to West Nyack
- Arkansas governor allocates $42 million for water infrastructure projects
- Federal judge finds Flint, Mich, in contempt over lead water pipe crisis
Comments