Williams Partners Takes Legal Action over Pipeline Construction Stoppage
Williams Partners L.P. today filed a Motion for Clarification of an administrative stay issued yesterday by the U.S. Court of Appeals for the District of Columbia Circuit of the Federal Energy Regulatory Commissions’ authorization of the company’s Atlantic Sunrise natural gas pipeline project. The purpose of the administrative stay is to give the court sufficient opportunity to consider an emergency motion filed by project opponents last week requesting FERC extend a comprehensive four-year permitting process even further.
“Atlantic Sunrise has undergone a nearly four-year, extensive review process and is operating and being constructed in compliance with all state and federal permits,” said Micheal Dunn, Williams Partners’ chief operating officer. “These current actions by opponents of American energy are, this morning, idling thousands of workers in Pennsylvania and could delay the benefits of low-cost energy delivery to millions of American families. It is important to stress that this temporary stay is administrative and not related to the project’s execution or its compliance with applicable federal or state regulations or permit conditions. It is merely intended to give the court sufficient opportunity to consider the motion recently filed by project opponents and is not a ruling on the merits of that motion.”
Construction on the project broke ground in Pennsylvania on Sept. 15, 2017. While Williams Partners has ceased construction activities until the temporary stay is lifted, the company believes it is prudent and will continue to maintain environmental controls related to construction to remain in compliance with Federal and Pennsylvania permits, while protecting the environment.
During peak construction periods, the Atlantic Sunrise Project is anticipated to directly employ approximately 2,300 people in 10 Pennsylvania counties. In addition, it could support an additional 6,000 jobs in related industries and generate up to $1.6 billion in economic activity, according to researchers at Pennsylvania State University.
The nearly $3 billion project, which is designed to increase natural gas deliveries by 1.7 billion cubic feet per day, is expected to be placed into full service in mid-2018.
Related News
From Archive
- Tunnel boring machine ‘Clack-A-Mole’ nears one-third completion in Oregon outfall project
- Lynchburg, Va., breaks ground on largest-ever Blackwater CSO tunnel project
- Texas A&M weighs underground transit plan with Elon Musk's Boring Co. to reduce campus traffic
- Wyo-Ben’s Max Gel, Max Bore HDD system boost drilling efficiency, performance
- Federal court halts permits for 32-mile Tennessee gas pipeline project
- Wisconsin proposes new PFAS drinking water standards to align with federal rules
- Elgin, Ill., joins EPA drinking water initiative to accelerate lead pipe replacement
- Dog River pipeline replacement in Oregon improves water supply with new HDPE pipe
- Leaking wastewater systems named top source of San Diego River contamination, study finds
- New Portable Welding System From Miller
Comments