CHARLESTON, W.Va. (AP) — A federal judge tells developers of the Mountain Valley Pipeline he won’t order all landowners in its West Virginia lawsuit to respond by Dec. 4 to motions for summary judgment for rights of way available under federal regulations.
The Charleston Gazette-Mail reports that U.S. District Judge John Copenhaver at a status conference Thursday said he wants the developers to locate landowners and serve them with court papers.
The pipeline would extend south for 195 miles (315 kilometers) from north-central West Virginia through 11 counties to the Virginia state line, and nearly 110 miles (175 kilometers) through six counties in Virginia.
Pipeline lawyers said in two federal suits that acquiring easements through condemnation is necessary as the developers have been unable to negotiate agreements with about 400 landowners.
Related News
From Archive
- DeLa Express seeks FERC approval for Permian-to-Louisiana gas pipeline project
- OSHA penalizes Houston contractor over safety violations resulting in worker's death
- Fiber infrastructure has no known expiration date, Fiber Broadband Association research concludes
- Nevada OSHA fines Elon Musk's Boring Company over safety violations in Vegas tunnel project
- Damage prevention and safety: Turning awareness into action
- Ditch Witch 1030
- Michigan lawmakers introduce bills to create septic codes throughout the state
- Indiana American Water to gain 8,000 water customers with Silver Creek Water acquisition
- Arkansas governor allocates $42 million for water infrastructure projects
- Federal judge finds Flint, Mich, in contempt over lead water pipe crisis