Judge to Hear Arguments on Tribe’s Pipeline Contingency Plan
BISMARCK, N.D. (AP) — A federal judge in Washington, D.C., will accept arguments over the next month on whether the developer of the Dakota Access pipeline must stage equipment near an American Indian reservation in southern North Dakota to respond to any oil spill under the Missouri River.
The idea is part of a fallback plan proposed by the Standing Rock Sioux tribe in August in case U.S. District Judge James Boasberg eventually decides to allow the four-state pipeline to continue operating while federal officials do more study on the $3.8 billion project’s impact on the tribe.
Boasberg ruled on Oct. 11 that oil could keep flowing from western North Dakota through South Dakota and Iowa to a distribution point in Illinois, as it has been since June 1. President Donald Trump earlier this year pushed through the pipeline’s completion.
On Wednesday, Boasberg conferred with attorneys on both sides of an ongoing tribal lawsuit against the pipeline and set a timeline for arguments on Standing Rock’s proposal. It includes increased public reporting of pipeline issues such as repairs, and implementation of an emergency spill response plan — including equipment staging — at the crossing beneath the Missouri River’s Lake Oahe reservoir.
The tribe gets its water from the reservoir and fears harm from any spill. Standing Rock is the leader of four Sioux tribes hoping to convince Boasberg to shut down the line, which Texas-based developer Energy Transfer Partners maintains is safe.
Boasberg won’t make a decision until the Army Corps of Engineers, which permitted the project, completes more study that he ordered in June on the pipeline’s impact on Standing Rock. The additional review isn’t likely to be completed until next spring, according to the Corps.
Boasberg in his ruling allowing pipeline operations to continue noted that the Corps and ETP had not yet expressed their positions on the tribe’s “alternative relief” plan and said he would hear arguments on the matter. He’ll make a decision on the proposal sometime after mid-November under the timeline for arguments that he set Wednesday.
Related News
From Archive
- Tunnel boring machine ‘Clack-A-Mole’ nears one-third completion in Oregon outfall project
- Lynchburg, Va., breaks ground on largest-ever Blackwater CSO tunnel project
- Texas A&M weighs underground transit plan with Elon Musk's Boring Co. to reduce campus traffic
- Wyo-Ben’s Max Gel, Max Bore HDD system boost drilling efficiency, performance
- Federal court halts permits for 32-mile Tennessee gas pipeline project
- Wisconsin proposes new PFAS drinking water standards to align with federal rules
- Elgin, Ill., joins EPA drinking water initiative to accelerate lead pipe replacement
- Dog River pipeline replacement in Oregon improves water supply with new HDPE pipe
- Leaking wastewater systems named top source of San Diego River contamination, study finds
- New Portable Welding System From Miller
Comments