West Virginia Regulators Stop Construction Halt on Rover Pipeline Segments
MORGANTOWN, W.Va. (AP) – State environmental authorities lifted their order halting Rover Pipeline construction on two segments where it found permit violations damaging streams in northern West Virginia.
Inspectors in April, May, June and July found erosion-control failures that left sediment deposits in creeks and streams.
The Department of Environmental Protection ordered Rover Pipeline LLC on July 17 to stop.
The DEP says inspections Wednesday show permit violations were corrected.
One segment extends 36 miles (58 kilometers) from Ohio through Tyler and Wetzel counties to a compressor station at Sherwood in Doddridge County.
Another runs for six miles (10 kilometers) through Doddridge County.
Construction wasn’t halted on two other West Virginia segments.
The 700-mile (1,126-kilometer) Rover Pipeline will carry natural gas from shale deposits in West Virginia and Pennsylvania across Ohio and into Michigan.
Related News
From Archive
- Glenfarne Alaska LNG targets late-2026 construction start for 807-mile pipeline project
- U.S. water reuse boom to fuel $47 billion in infrastructure spending through 2035
- $2.3 billion approved to construct 236-mile Texas-to-Gulf gas pipeline
- Major water pipe break in Puerto Rico hits over 165,000 customers
- Potomac River Tunnel project enters construction phase beneath Washington, D.C.
- Pennsylvania American Water launches interactive map to identify, replace lead water service lines
- Trump's tariffs drive $33 million cost increase for Cincinnati sewer project
- Utah city launches historic $70 million tunnel project using box jacking under active rail line
- Tulsa residents warned after sewer lines damaged by boring work
- Fatal trench collapse halts sewer construction in Massachusetts; two workers hospitalized

Comments