Crews: 2 Approaches to Restore Outer Banks Islands' Power
RODANTHE, N.C. (AP) — Crews are taking two approaches to restore power to two North Carolina Outer Banks islands.
Cape Hatteras Electric Cooperative spokeswoman Laura Ertle said in a statement that crews are digging up damaged cables to splice together. The utility also is looking at an overhead transmission line from the Bonner Bridge to existing lines on Hatteras Island.
Ertle said crews are working on both plans until it’s clear which is fastest and safest. She says depending on the approach, repairs could take one to two weeks.
Tourists were evacuated from Hatteras and Ocracoke islands because of Thursday’s outage.
Gov. Roy Cooper is visiting the bridge Monday where three transmission cables were damaged by a construction crew. Cooper also will visit businesses in Rodanthe, south of the bridge on Hatteras Island.
Related News
From Archive
- Tunnel boring machine ‘Clack-A-Mole’ nears one-third completion in Oregon outfall project
- Lynchburg, Va., breaks ground on largest-ever Blackwater CSO tunnel project
- Texas A&M weighs underground transit plan with Elon Musk's Boring Co. to reduce campus traffic
- Wyo-Ben’s Max Gel, Max Bore HDD system boost drilling efficiency, performance
- Colorado's Wolf Creek Pass tunnel drainage project begins
- Wisconsin proposes new PFAS drinking water standards to align with federal rules
- Elgin, Ill., joins EPA drinking water initiative to accelerate lead pipe replacement
- Dog River pipeline replacement in Oregon improves water supply with new HDPE pipe
- Leaking wastewater systems named top source of San Diego River contamination, study finds
- New Portable Welding System From Miller
Comments