July 2019 Vol.74 No. 7
Energy Pipeline Projects Update
NGL - SemCAMS Midstream and Keyera
Canada
SemCAMS Midstream and Keyera
Project: Canada Liquids Pipeline System
Location: Northern Midland Basin
Capacity: 100,000 bpd, expandable to 200,000 bpd
Dimensions: 171 miles (275 km); 16-inch condensate, 12-inch NGL pipelines.
Completion: 2022
Comments: The pipeline will connect the liquids-rich Montney and Duvernay production areas of northwestern Alberta to the fractionation and condensate hubs in Fort Saskatchewan, Alberta. Construction is expected to begin in the second half of 2020.
Comments