Lightpath to build 392-mile underground fiber route linking Columbus, Chicago
(UI) — Lightpath plans to construct a nearly 392-mile underground fiber route connecting Columbus, Ohio, and Chicago, marking the company’s first organically developed long-haul network build.
The project includes approximately 327 miles of new underground multi-conduit fiber infrastructure spanning three states. Construction will be completed in phases, with the full route expected online by the end of 2028.
The corridor is designed to connect two rapidly growing data center markets and will incorporate eight LightCube data centers along the route, including seven new facilities. The network will support dark fiber, conduit, colocation and high-capacity connectivity services for hyperscale, carrier and enterprise customers.
Lightpath CEO Chris Morley said the project reflects growing demand for long-haul fiber infrastructure tied to AI and cloud computing growth.
“The Columbus-to-Chicago corridor reflects sustained hyperscale demand for high-capacity, long-haul fiber,” Morley said.
The southern portion of the route between Columbus and South Bend is expected to be the first segment placed into service. Additional amplification infrastructure is also being evaluated to increase network capacity.
The project expands Lightpath’s broader effort to build underground fiber infrastructure supporting large-scale data center and enterprise connectivity markets across the U.S.
Related News
From Archive
- OSHA investigates fatal trench collapse at Conroe construction site
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- Oil pipeline struck during fiber optic construction spills into L.A. storm drains
- Fiber drilling strike triggers major sewer failure, lawsuits in Florida
- OSHA cites Alabama builder after fatal trench collapse
- Race Communications breaks ground on Bakersfield fiber network
- Final Lake Erie sewer tunnel project set to begin after decades-long $3 billion effort
- Inside Infrastructure: Utility locators warn of systemic failures in damage prevention process
- Senate passes PIPELINE Safety Act aimed at strengthening buried utility protection

Comments